Major network reinforcement project for Royal Military Academy This major redevelopment of a Grade II listed building was taking place right in the heart of London. Programme This major redevelopment of a Grade II listed building was taking place right in the heart of London. The work was highly sensitive as it involved a London ‘landmark’ building — it needed to support 330 units and had the potential to disrupt a busy commuter route. Our team’s technical and civils capabilities came to the fore. Our solution We reinforced the network by upgrading an existing substation on site and building a new one. We also installed over 3,800m of high voltage cable from the Eltham grid substation to the site. Careful planning and close liaison with Greenwich parks and highways ensured the infrastructure installed by our team caused minimal disruption to London’s commuters. A proven track record 3800m HV cable installed. 330 units required energy supply. 1 upgraded substation and a brand-new build. Read our case studies Post navigation Case StudyCase Study